On substantial completion of construction activities, Contractor mobilizes its commissioning team to initiate pre-commissioning activities in a phased manner.
The objective of pre-commissioning is to ensure that the pipeline as well all the facilities have been completed according to the Project Specifications and that commissioning and operation will take place safely and effectively.
Also during the pre-commissioning should be verified that all the relevant data with the commissioning of the pipeline has been received and that the commissioning procedure is presented and discussed with all personnel involved.
Another important aspect which has to be verified during this procedure is that all the necessary drawings, technical information, and O & M manuals have been received and that the operating plan has been existing .
Pre-commissioning may therefore be defined as all the checks that are to be completed prior to commissioning being permitted to commence.
In addition of the above information is to update in parallel Icaps logiciel ( Integrated Commissioning and Progress System) in order to commissioning will commence